• THE GRID
The 10x Gap
An insurance broker just put a price on the gap everyone can feel.
Howden, one of the world's largest brokers, released its "Insuring the Data Centre Supercycle" report on September 15. One number tells the story. Since 2000, U.S. data center power demand has climbed 19% a year. Grid capacity? Just 2%.
That's a 10x mismatch.
Lawrence Berkeley National Laboratory projects data centers could use 12% of all U.S. electricity by 2028. In 2018, before the AI rush, their share was 1.9%. A six-fold jump in a decade. No industry in modern American history has scaled its electricity use this fast.
The grid was not built for this pace.
"There is a real mismatch in timing between how quickly data centers want power and how quickly the grid can expand."
After 25 years of flat demand, Gramlich told Fortune, utilities "got out of practice on building new infrastructure." Grid capacity is slow to build. Thousands of parts must work in concert. It takes years of study and planning. The AI boom didn't wait.
DC Demand
19%/yr
| Grid Capacity
2%/yr
|
Off-Grid by 2030
110 GW
| Lost Rev / Site
$2.4B
|
Stop Trading Until You Read This
Before you place another trade...
...make sure you use this 5-part "Safe Trade Options Formula" that makes every trade a SAFE TRADE.
Once you start using this, I don't think you'll ever trade again without it.
OK?
The delays are already here. Howden says power constraints add two to six years to the most constrained builds. The largest data center sites earn close to $400 million a year. A six-year slip means up to $2.4 billion in lost revenue. At a single site.
The forward math is even harder. Data centers held about 5% of U.S. grid capacity in 2025. To keep that share through 2030, they would need 58% of their power from off-grid sources. That's 110 gigawatts. Howden itself calls that target unlikely. But staying fully on the grid means longer queues and bigger delays for everyone.
Kathryn Burke at Marsh insurance told Fortune she expects 50% to 60% of data center projects to miss their planned timelines.
The political walls are going up too. On Nov. 3, voters rejected data center projects in 40 of 41 local ballot measures. Maine is prepping a second statewide moratorium. Texas' governor-elect wants a construction freeze. Delaware signed the first state law requiring large energy users to bring their own power.
Projects, capital, and timelines are all running into the same wall: a grid that can't grow fast enough.
Insurers don't speculate. They price risk. When the people writing the policies say the grid can't keep up, the smart money pays attention.
Jon Najarian's #1 Elon Musk Trade for 2027
Elon Musk is building an AI empire in space. And Hall of Fame Trader Jon Najarian says there's one tiny company he may not be able to build it without.
Elon has already secured the right to acquire up to 15% of the company. And its shares are still trading under $25.
• RESISTANCE
The $5 Billion Shift
$5.13 billion.
That's how much of the data center grid buildout landed on other customers last year. Not on data centers. On everyone else.
A Cornell University study published November 9 in Nature Energy traced the money. Researchers Cheng Feng and Fengqi You analyzed four major U.S. power grids from 2020 to 2025. Their finding: data centers paid just 38% of the $8.25 billion in infrastructure costs tied to their growth in 2025.
In 2025, data centers paid $3.12 billion of an $8.25 billion infrastructure bill tied to their growth—just 38%. Households covered the other 62%. The heaviest burden fell on rural and lower-income communities. Across four major U.S. power grids, transmission spending surged from $2 billion in 2020 to $34 billion in 2025.
The wholesale price impact was sharp. In California's southern Bay Area, data centers pushed prices up nearly 20%. Around Dallas–Fort Worth, the jump approached 17%. Virginia saw 15%. These aren't small shifts. Wholesale costs make up 30% to 50% of a household power bill.
The Cornell researchers call the pattern a "paradoxical mismatch." Rural and lower-income households bore the largest shares despite using the least power.
Utilities keep filing for more. Through the first three quarters of 2026, rate increase requests hit $23.1 billion. The third quarter alone set a record at $4.5 billion.
The math is simple. Data centers use the grid. Households pay for it. Voters figured this out on Nov. 3. Regulators are still catching up.
• BLACKOUT WATCH
Less Than Half the Power When It Counts
NERC's winter outlook came out last week. The headline numbers look calm. The details don't.
The battery haircut. NERC's 2026–2027 Winter Reliability Assessment landed November 18. The headline sounds great: on-peak capacity grew 26.2 GW over last winter, led by batteries and gas. But look at the fine print. Batteries added 20.6 GW of nameplate capacity this year. At winter peak, only 9.2 GW shows up. That's a 55% cut. The grid's fastest-growing resource delivers less than half its rated power when cold weather hits.
Demand is speeding up. NERC says aggregate peak demand grew 21 GW—2.6%—since last winter. That's faster than the year before. Data centers are the main driver. Even with 26.2 GW of new supply, the gap between new demand and new capacity is razor-thin. One bad cold snap could erase the cushion. And NERC warns this year's El Niño adds a layer of risk that doesn't show up in averages.
Everyone counts the megawatts being added. Few count what shows up on the coldest night. That's the number that matters.