• THE GRID
The Clock Is Ticking on Every Grid Operator in America
Yesterday was a deadline. A big one. And most people missed it.
August 3 was the last day for America's six regional grid operators to ask FERC for more time. More time to explain why their rules for connecting data centers to the grid are fair. Or to admit they need new ones.
On June 18, FERC did something it had never done before. It fired off show cause orders to all six RTOs at once. PJM. MISO. SPP. ISO-NE. NYISO. CAISO. Every one of them.
The message was blunt. Prove your rules still work. Or fix them. You have 60 days.
"We want to act quickly. We want to move on it."
When Starlink Completes Its Global Takeover...
It's set to connect 3 billion people who've never had reliable internet.
That's the biggest connectivity explosion in human history.
Wall Street is focused on SpaceX.
But the smartest money is looking at a backdoor play almost no one's talking about.
A Potential IPO company already positioned to profit from every single new Starlink user — in 170 countries — before they ever go public.
And if you act fast, you can invest now at $0.52/share.
But don't wait.
Their last round sold out with 59,000+ total investors. Once word spreads — it could be too late.
The orders target a broken system. Right now, data centers can "shop around" — file requests with several utilities at once to find the fastest, cheapest path to power. That clogs the queue. It wastes time. Worse, it inflates demand forecasts with projects that never get built, which drives up costs for everyone else.
FERC wants that to stop. The new rules would force data centers to post real money before they get in line. Credit support tied to megawatt capacity. Escalating payments at each study phase. If a project is fake, the developer eats the cost — not your local ratepayer.
And behind-the-meter tricks? FERC is targeting those too. The orders say that netting on-site power against grid charges is "unjust and unreasonable." That's a direct shot at the 101 GW of behind-the-meter gas generation data centers have announced.
RTOs Ordered
6 of 6
| Response Deadline
Aug 17
|
PJM Peak (Jul 2)
168,158 MW
| Prior Record (2006)
165,563 MW
|
The timing matters. Just a month ago, PJM hit an all-time peak of 168,158 MW during the July 2 heat wave. That broke a 20-year record. PJM used every generator it had. The DOE had to issue emergency orders — again — so plants could run past their pollution limits.
A PJM spokesperson said afterward that the grid used roughly 3.25 GW of emergency generation to get through it.
So FERC is doing two things at once. Speeding up the queue. And making sure whoever joins it can actually pay for it.
The RTOs that asked for extra time yesterday can get up to 90 more days. Those that didn't must respond by August 17 with real tariff changes — or defend every line of their current rules.
This is the most aggressive grid reform effort in a generation. And two weeks from now, we'll see which grid operators are ready — and which ones aren't.
• RESISTANCE
833 Groups. 49 States. The Backlash Has a Zip Code Now.
At the end of 2025, there were 396 active groups fighting data center projects across the country. By March 2026, that number hit 833.
It doubled in one quarter.
833 active opposition groups across 49 states as of March 2026, up from 396 at year-end 2025. In Q1 alone, 75 projects worth $130 billion were blocked or delayed — matching the total for all of 2025. Source: Data Center Watch via Newsweek/Brookings.
This isn't just local NIMBYism anymore. Brookings published a report last week calling it a national political force. Opposition groups have petition counts from Q1 that nearly match the entire second half of 2025.
And the bills keep climbing. Utilities filed a record $9.2 billion in rate increase requests in Q2 2026 alone — 26% more than the prior Q2 record. That brings the first-half total to $18.6 billion.
"Summer is when Americans pay attention to what electricity costs because their utility bills are often higher," said Charles Hua, founder of PowerLines. "The pressure on household energy bills isn't easing."
So you have rising bills on one side. And a flood of new power demand from data centers on the other. Communities are caught in the middle — and they're organizing faster than the industry expected.
The price of consent is now a line item in every data center budget. Developers who don't budget for it are the ones getting blocked.
• BLACKOUT WATCH
Three Risks Nobody Wants to Talk About
The capex cliff is coming. Hyperscaler spending is up 76% this year to roughly $673 billion. But UBS forecasts growth drops to 25% in 2027 and just 6% in 2028. That's a massive deceleration. Investors are already rotating out of chipmakers and into the hyperscalers themselves. If spending slows faster than expected, every grid upgrade built for load that doesn't show up becomes a stranded cost — paid by ratepayers.
NERC's "adequate" isn't as safe as it sounds. The 2026 Summer Reliability Assessment says all regions can handle normal peaks. Good news. But three areas — New England, Saskatchewan, and the Pacific Northwest — face elevated risk under extreme heat. And we just lived through extreme heat. On July 2, PJM used every generator it had and still needed 3.25 GW of emergency power. NERC also flagged that large loads have unexpectedly dropped off the grid in both ERCOT and the Eastern Interconnection. Those sudden swings catch operators off guard.
The DOE is quietly propping up the grid. Since May 2025, the Department of Energy has used its Section 202(c) emergency authority more than 40 times. It has stalled the retirement of at least 4.4 GW of coal plants. Those units aren't even counted in NERC's reserve calculations — they're a shadow buffer. If the political winds shift and those plants close, the margin disappears overnight.
The grid looks stable on paper. But paper doesn't sweat through a heat wave. The real margin is thinner than anyone is pricing in.
Disclaimer*: Please read the offering circular and related risks at invest.modemobile.com. This is a paid advertisement for Mode Mobile’s Regulation A+ Offering.
Mode Mobile recently received their ticker reservation with Nasdaq ($MODE), indicating an intent to IPO in the next 24 months. An intent to IPO is no guarantee that an actual IPO will occur.
The Deloitte rankings are based on submitted applications and public company database research, with winners selected based on their fiscal-year revenue growth percentage over a three-year period.
Pro forma revenue and EBITDA, includes full year numbers of the businesses acquired throughout 2025.


