Three New Governors Just Won on a Promise to Freeze Data Center Construction

Over $170 billion in data center projects are already stalled or blocked. The fight just moved up a floor.

The Capital Current
The Capital Current

Nov 17, 2026

• THE GRID

PJM Just Forecast a Record Winter Peak. Data Centers Wrote the New Math.

147,500 megawatts. That's the number PJM posted on November 5 as its peak winter demand forecast. If the cold hits hard enough, it would set a new all-time winter record for the largest grid in America.

Four years ago, that number was 7,500 MW lower. What changed? Data centers. Big ones. Lots of them.

PJM covers 13 states and D.C. It runs power for 65 million people. And its winter math is shifting fast. The grid says it has 182,426 MW of capacity on hand. That sounds like plenty of room. But reserves are thinner than they look.

PJM Winter Peak Forecast
147,500 MW
Demand Growth Since 2022
+7,500 MW
PJM Capacity Available
182,426 MW
NYISO Winter Cushion
4.84 GW

A New Independent “Federal Reserve” Has Just Emerged in America

America has a new "Federal Reserve."

Not the one in Washington.

A new private financial power structure backed by six global financial giants controlling roughly $24 TRILLION.

And it's helping direct as much as $500 BILLION toward one of the world's most sought-after resources.

[See who's behind America's new "Federal Reserve."]

2.2 MILLION new millionaires could emerge over the next five years.

And on November 30th, the billionaire leading this transformation is scheduled to speak in Washington, D.C.

There are three steps you can take to prepare.

Including one stock ticker being given away FREE in this presentation:

[Watch the presentation and get the ticker here.]

PJM also expects to export about 3,200 MW to neighbors. That eats into the buffer. And NERC's CEO just gave the bluntest warning I've read in months.

❝

"While that is good news, the bulk power system continues to face serious reliability risks during the winter period."

— Jim Robb, President and CEO, NERC (November 10, 2026)

It's not just PJM. New York's grid operator says 5,400 MW of generation could go dark on the coldest days due to fuel limits. Most of that sits in eastern New York, where gas pipelines max out when everyone needs heat and power at once. NYISO's safety cushion above peak demand? Just 4.84 gigawatts.

Add in the Super El Niño. Amperon's winter outlook says it will split the country — a wet south, a warm and dry north. That means less wind and less hydro right when reserves are slim.

I keep coming back to that 7,500 MW. Five percent growth in four years. Nearly all of it from large-load customers, which is code for data centers. The grid held last winter through a brutal cold snap. But margins are shrinking, and the load keeps climbing.

Winter is the test that shows whether the grid can keep up with the AI boom. Right now, the answer is: barely.

Jon Najarian's #1 Elon Musk Trade for 2027

Elon Musk is building an AI empire in space. And Hall of Fame Trader Jon Najarian says there's one tiny company he may not be able to build it without.

This is his #1 Elon Musk trade for 2027.

Elon has already secured the right to acquire up to 15% of the company. And its shares are still trading under $25. 

More details here…

• RESISTANCE

Three New Governors Just Promised to Freeze Data Centers

On election night, Gina Hinojosa beat Greg Abbott in Texas. Her first pledge? A moratorium on new data center builds. Texas holds more than 25% of all planned U.S. data center capacity.

She wasn't alone. Amy Acton won Ohio on a conditional moratorium platform. Georgia elected a governor who ran on tighter oversight. Democrats also took Nevada.

⚠ Capacity at Risk

Goldman Sachs says states now controlled by leaders who back data center restrictions hold 45% of planned U.S. data center capacity. Texas alone accounts for a quarter of all planned U.S. capacity.

This goes beyond local ballot measures. Governors hold executive power. They can pause permits, yank tax breaks, and rewrite rules. Abbott had already imposed his own data center moratorium before losing. Hinojosa says she'll keep it — and extend it until lawmakers pass stricter AI rules.

The numbers are stark. Across 46 states, 583 moratoriums are now in force. Voters passed restrictions in 46 of 47 ballot measures this cycle. But a town council vote is one thing. A governor's pen is another.

Between January 2024 and May 2026, at least 46 data center projects worth more than $170 billion were blocked or stalled by local fights, per IDCA. Now the fights have moved to the top floor.

The people who sign permits just got replaced by people who promised not to.

• BLACKOUT WATCH

Three Risks the Market Hasn't Priced

I went looking for what could go wrong this winter. I found three things. Not one of them shows up in an earnings model.

  • New York's fuel gap. NYISO models 5,400 MW of generation as gone on the coldest winter days. The cause: fuel can't reach the plants. East Coast distillate stocks are below normal. Oil prices are jumpy. Winter Storm Fern last January showed what happens when gas competes with heat — the grid nearly broke. New York's total winter cushion above peak demand is just 4.84 GW. One bad week could eat that whole margin.

  • El Niño meets record load. Amperon's winter outlook flags a Super El Niño that could cut wind and hydro output across the northern U.S. — right when PJM projects record peak demand of 147,500 MW. Less clean power flowing in means more stress on gas plants already running near capacity. Texas faces tail risk in both directions: a warm spell could crash prices, while a surprise freeze could strain ERCOT like 2021.

  • The governor effect. Yorkville Ives' Dan Ives, one of Wall Street's biggest AI bulls, now says capex might peak in 2027 due to the political wave. If newly elected governors in Texas, Ohio, and Georgia follow through on moratoriums, over $170 billion in stalled or blocked projects stays frozen. The grid upgrades those projects would have funded don't get built. And utility earnings growth tied to data center load slows down just as rate cases pile up.

The grid is heading into its hardest winter in years with thinner margins, weaker fuel supply, and a political class that just got elected to say no.