Venture Global Ordered 11.5 GW of Gas Turbines. Zero Go to the Grid.

Each power island is 720 MW. They run on Venture Global’s own gas, on its own land, with no utility contract.

The Capital Current
The Capital Current

Oct 20, 2026

• THE GRID

An LNG Giant Just Ordered 11.5 Gigawatts of Gas Turbines. Not for the Grid.

Venture Global ships gas overseas. That's been its whole story. Until this month.

On October 9, the LNG exporter signed frame deals with GE Vernova and Baker Hughes for up to sixteen power-island units. Each one: 720 megawatts. Total: roughly 11.5 gigawatts of new gas-fired power.

None of it goes to the grid.

Every watt runs behind the meter. "Island mode," the company calls it. These plants sit on Venture Global's own land. They burn Venture Global's own gas. They feed power straight to data centers. No grid tie. No utility contract. No PJM queue.

New Islands
11.5 GW
 
Per Unit
720 MW
 
VG Fleet Now
4.5 GW
 
U.S. BTM Online
~2 GW

Elon Musk: This Could be 180 Times Bigger than SpaceX IPO

Elon Musk is on record predicting this new opportunity is set to be 180 times bigger than the SpaceX IPO.

That IPO minted 4,400 millionaires overnight.

If this is 180 times bigger…

Just imagine how many more Americans will become millionaires.

Will you be one of them? Click here now.

Line those up. About 2 GW of behind-the-meter data center power is running in the U.S. today. Venture Global alone has 4.5 GW ordered, under construction, or operating. And it just ordered parts for 11.5 GW more.

One company. A pipeline already twice the size of everything running nationwide.

❝

"Simply put, Texans must come first. Data centers must pay their own way."

— Texas Governor Greg Abbott, news release, September 2026

The irony is sharp. States are freezing data center permits. Texas paused them all. FERC just blocked PJM's plan to manage big new loads. And yet Venture Global's model skips every one of those fights.

No permit queue. No rate case. No curtailment debate.

That's the real signal here. The grid is so slow, so tangled in rules, that an LNG shipper saw a faster path. Build your own power plant. Burn your own gas. Sell the rest as compute.

Up to 1.9 Bcf/d
Estimated gas burn at full build-out — roughly 3.5% of total U.S. gas production

At full build, the gas burn could hit 1.9 billion cubic feet per day. That's a lot of molecules diverted from export. That could push prices up for everyone else who heats with gas or runs a gas plant.

The first equipment order is due by year-end. Target: up to 10 GW of AI compute by 2034.

The grid didn't lose this race. It never entered. And the companies that noticed first are building a shadow grid that answers to no utility commission.

Your Download Link Will Expire

If you still haven't downloaded my free "Safe Trade Options Formula" guide...

...please take a few seconds and download it right now before your new temporary download link expires.

I eventually plan to charge money for this training, so do yourself a favor and download it now...

That way, no matter what it costs in the future, you'll have a free copy on your computer.

Make sense?

FREE: Safe Trade Options Formula << Download Now

• RESISTANCE

Georgia Just Approved the Biggest Data Center Power Deal in U.S. History. The Fine Print Is What Matters.

OpenAI's new data center in Effingham County, Georgia will draw 3.2 gigawatts. That's more power than the city of Atlanta uses.

Georgia's Public Service Commission approved the contract in late August. But it came with strings.

⚠ Ratepayer Alert

Georgia Power must deliver $15 per month in downward pressure on the average residential bill from 2029 to 2031 — roughly 75% higher than its prior $8.50 pledge. The utility also agreed not to recover any lost revenue from the OpenAI deal on the backs of existing customers.

PSC Chairman Jason Shaw called it the "strongest residential ratepayer protections" ever attached to a data center deal. That phrase tells you something. It means past deals had weaker ones. Or none at all.

Georgia Power customers have seen their bills rise about $43 per month since 2022 through a series of rate increases. The $16.3 billion capacity build-out the PSC approved, aimed largely at data centers, could cost ratepayers $50 to $60 billion over its life once financing costs are counted.

And Georgia is just one state. Nationwide, electric and gas utilities filed $4.5 billion in rate hike requests in Q3 alone. The nine-month total: $23.1 billion. The Q3 filings could touch 45.5 million customers.

The average U.S. home now pays 18.31 cents per kilowatt-hour. That's up 4.9% from a year ago, per EIA data through July.

Tech companies signed the White House Ratepayer Protection Pledge in March. But it was one page. Non-binding. No dollar figures. Georgia's PSC put real numbers on paper.

Now watch the other states. Will they demand the same, or keep signing blank checks?

• BLACKOUT WATCH

Three Risks Hiding in Plain Sight

  • The 3.8 GW vanishing act. On July 22, a single line faulted near Ashburn, Virginia. Data centers tripped off the grid in seconds. About 3.8 GW of load — roughly 3.8% of PJM demand — vanished. Lights flickered across the region. In 2024, a similar fault dropped 1.5 GW. The problem more than doubled in two years. NERC still has no binding "ride-through" rule for data centers. Any fault near a cluster can dump gigawatts with no warning.

  • The December deadline nobody talks about. In July, FERC ordered NERC to write the first mandatory reliability standards for data centers. Deadline: December 31, 2026. That's 72 days away. That's a tight clock for a brand-new class of rules. If it misses, data centers enter winter with no enforceable rules — just weeks after the FERC-NERC winter review found real barriers to using backup generation at large loads during storms Fern and Gianna.

  • The cash is running out. Hyperscaler capex is on pace to top $800 billion in 2026. But aggregate free cash flow has gone negative for the first time. Amazon's trailing free cash flow swung to negative $7.6 billion. Wall Street expects spending to slow in 2027. If it does, grid contractors booking record backlogs are building for customers who may not be able to pay. That's a credit risk dressed up as a growth story.

The market prices data center power as a sure thing. A line fault, a missed deadline, and a cash crunch say otherwise.

Keep Reading

All Articles

Subscribe

Privacy policy

Terms & conditions

© 2026 The Capital Current. All rights reserved.